WBHO
Commencement
December 2018
Completion
June 2020
Project Value
$12M
Project Location
Muchea, WA
Our Project Scope
The Garli Muchea North Project involved the delivery of major supporting infrastructure works associated with the Great Northern Highway, requiring close coordination with multiple contractors and stakeholders to ensure seamless integration with adjacent works.
Garli delivered approximately 8 kilometres of new road and bulk earthworks construction, supporting the overall upgrade of the corridor. The scope also included the installation of approximately 23 kilometres of new fencing, enhancing road safety, asset protection, and land management outcomes across the project area.
A significant landscaping component was delivered as part of the works, including the planting of approximately 600,000 seedlings, demonstrating Garli’s capability in managing large-scale environmental and rehabilitation works alongside civil construction activities.
Additional works included the supply and installation of road signage in accordance with project and authority requirements. Garli also undertook detailed interface coordination with WBHO, aligning its scope with WBHO’s 12-kilometre road construction works on the Great Northern Highway to ensure continuity of construction activities, program alignment, and safe delivery across shared work zones.